1.
Choose a site that drains well and if
possible has a natural slope for drainage.
|
|
2.
Measure the site and remove the organics. Grass and soil will
turn to muck after a good rain. You do not want this
contaminating your arena.
|
|
3.
When you have reached a solid base such as clay. Have the
area leveled and sloped to 1% grade to the lowest point.
Depending on how much you have removed from the site you will
need to build it back up with a compactable aggregate such as
pit run. This is an inexpensive way to build your subsurface
back up to ground level.
|
|
4.
Next you will add 3/8" road crush or limestone screenings.
This layer will take a beating from your horses hooves. This
need to be as close to 100% compacted as possible. Sloped to 1%
and laser leveled. Depending on the traffic in your arena the
road crush should be approximately 4-6" It may also be called
stone dust. You do not want this layer to break up and
render your footing too deep.
|
|
5. You are now ready for Perfect
Rubber Mulch. Mix rubber with washed concrete sand or masons
sand for good results. These products have minimal fines and
will not break down as quickly when mixed with Perfect Rubber
Mulch.
|
|
6.
Apply Perfect Rubber Mulch to the raked sand. You can mix
this in as you go or let the horses do the work. Note the round
pen has a 2x6 surround, this helps keep your sand and rubber in
place.
|
|
7.
Enjoy a safe and resilient footing for years to come.
|